Hi!

Has anyone run into a problem when trying to select a date range? The first date box works as expected giving me access to all of the months and days. The second box for the ending range only give me access to the last week. (See Picture Below) I am running Fedora 31, Zoneminder 1.34.2

Thanks!

Image
cobash
Posts: 5
Joined: Mon May 20, 2019 3:42 pm

Re: Montage Review Calendar

Post by cobash »

Forgot to mention I tried this in IE, Chrome, and Firefox. I can manually edit the url and put in a different date and that works fine. Just not the clickable calendar.

Thanks!
User avatar
iconnor
Posts: 2900
Joined: Fri Oct 29, 2010 1:43 am
Location: Toronto
Contact:

Re: Montage Review Calendar

Post by iconnor »

The second calendar won't go before the first one. So if the start calendar is set to Feb 1st, then the second will not go lower than Feb 1st.
cobash
Posts: 5
Joined: Mon May 20, 2019 3:42 pm

Re: Montage Review Calendar

Post by cobash »

I understand and that's the way it used to work. But in the picture it is only going back 1 week. I have the first date set to February 1st and the second date is only letting me go back one week from the current date. In my case when I tested it on the 21st and it is only letting me select as far back as the 14th.
User avatar
iconnor
Posts: 2900
Joined: Fri Oct 29, 2010 1:43 am
Location: Toronto
Contact:

Re: Montage Review Calendar

Post by iconnor »

confirmed. Will fix for 1.34.5
cobash
Posts: 5
Joined: Mon May 20, 2019 3:42 pm

Re: Montage Review Calendar

Post by cobash »

Many thanks!!